City of Hayward Logo

Invest in Infrastructure Icon

Develop a Recycled Water Master Plan

Project Description

In FY 2024, staff initiated development of a Master Plan to guide design and construction efforts for Phase II of the Recycled Water Program. Phase II will involve increasing the recycled water customer base, which will require designing and constructing an expanded treatment facility to meet the increased demand.

Q4-FY24 Status Update (Updated Fiscal Year Quarterly):

Start Date: 07/08/2024 End Date: 11/28/2025 Percent Complete: 0%
City of Hayward, California | 777 B Street | Hayward, CA 94541 | 510-583-4000